£61million Center Parcs Woburn Forest project

The highly complex logistical operation to create Center Parcs’ fifth UK village sees the construction of 109 lodge clusters at the Woburn site, with 16 different accommodation configurations across Woodland, Executive and Exclusive lodge specifications. ISG has worked closely with local timber frame specialists, Kingspan Timber Solutions to ensure that more than 38,000 wall components and 20,000 timber trusses have been delivered to site in the correct sequence, following the completion of ground floor slabs by ground work specialist Hiretest.